Presence of back-up generators

From Electrical Installation Guide

Jump to: navigation, search
Scope and content of Wiki EIG
General rules of electrical installation design
Connection to the MV utility distribution network
Connection to the LV utility distribution network
MV & LV architecture selection guide
LV Distribution
Protection against electric shocks
Sizing and protection of conductors
LV switchgear: functions & selection
Protection against voltage surges in LV
Energy Efficiency in electrical distribution
Power factor correction and harmonic filtering
Power harmonics management
Characteristics of particular sources and loads
PhotoVoltaic (PV) installation
Residential electrical installations
ElectroMagnetic Compatibility (EMC)


(Fig. D16)
Here we only consider LV back-up generators.
The electrical power supply supplied by a back-up generator is produced by an alternator, driven by a thermal engine.
No power can be produced until the generator has reached its rated speed. This type of device is therefore not suitable for an uninterrupted power supply.
According to the generator’s capacity to supply power to all or only part of the installation, there is either total or partial redundancy.
A back-up generator functions generally disconnected from the network. A source switching system is therefore necessary.
The generator can function permanently or intermittently. Its back-up time depends on the quantity of available fuel.



FigD16.jpg







Fig. D16: Connection of a back-up generator

The main characteristics to consider for implementing LV back-up generator:

  • Sensitivity of loads to power interruption,
  • Availability of the public distribution network,
  • Other constraints (e.g.: generators compulsory in hospitals or high-vise buildings)

The presence of generators can be decided to reduce the energy bill or due to the opportunity for co-generation. These two aspects are not taken into account in this guide.
The presence of a back-up generator is essential if the loads cannot be shed for an indefinite duration (long interruption only acceptable) or if the utility network availability is low.
Determining the number of back-up generator units is in line with the same criteria as determining the number of transformers, as well as taking account of economic and availability considerations (redundancy, start-up reliability, maintenance facility).